Tor Bay Harbour

Harbour Masters Notice 03/19

Victoria Breakwater Sea Defence Works Update

Back to Notices

Update - Victoria Breakwater, Brixham Sea Defence Work

From 15 January 2019

Mariners are advised that works have now commenced on the installation of the sea defences at the bull nose end of Victoria Breakwater by the contractors.  Please ensure a wide berth is given to the barge and safety boats whilst in operation.  Hourly updates on operational movements will be provided by the contractors on channel 16.

The Breakwater will remain open to the public but there will be a manned, temporary rolling easement fence on the structure located 50 meters on this side of the barge position. The Breakwater will be closed at night, out of working hours, this will continue on a daily basis during the week until further notice.

Adam Parnell

Tor Bay Harbour Master